SAP Exam C_TS422_2022 Topic 2 Question 28 Discussion

Actual exam question for SAP's C_TS422_2022 exam
Question #: 28
Topic #: 2
[All C_TS422_2022 Questions]

What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching? Note: There are 2 correct answers to this question

Show Suggested Answer Hide Answer
Suggested Answer: B, D

Contribute your Thoughts:

Ethan
2 days ago
Definitely B) Teardown time and D) Setup Time. Minimizing these tasks can significantly improve the efficiency of the operations.
upvoted 0 times
...
Derick
16 days ago
I agree with both of you. Queue and Teardown time can be reduced with the right settings.
upvoted 0 times
...
Gennie
20 days ago
I think the correct answers are B) Teardown time and D) Setup Time. Reducing these time elements can help optimize the midpoint scheduled operations.
upvoted 0 times
Steffanie
5 hours ago
I agree, reducing teardown time and setup time can definitely help optimize operations.
upvoted 0 times
...
...
Lisha
21 days ago
I believe Setup Time can also be reduced with reduction strategy settings.
upvoted 0 times
...
Carisa
27 days ago
I think the time element that can be reduced is Teardown time.
upvoted 0 times
...