SAP C_TS422_2021 Exam - Topic 6 Question 3 Discussion
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
B) Increase the capacity supply in a time-phased interval. and D) Form optimum sequences to reduce setup times. and E) Determine a time period with available capacity on the planning board.
A) Execute an infinite production planning run for the critical resources.
C) Reduce the planning window.