SAP C_TS422_2021 Exam - Topic 5 Question 42 Discussion

Actual exam question for SAP's C_TS422_2021 exam
Question #: 42
Topic #: 5
[All C_TS422_2021 Questions]

You are working with planning strategy 40 (Planning-with-final assembly)

When does consuption of planned independent requirements take places?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Malcolm
3 months ago
Are we sure about that? Sounds a bit off to me.
upvoted 0 times
...
Pok
3 months ago
Definitely when you create a planned order.
upvoted 0 times
...
Twana
3 months ago
I thought it was when you deliver a sales order!
upvoted 0 times
...
Rhea
4 months ago
Nope, it's actually when the MRP results are saved.
upvoted 0 times
...
Long
4 months ago
It's when you create a sales order, right?
upvoted 0 times
...
Rolf
4 months ago
I thought it was when you create a planned order, but now I'm second-guessing myself after reviewing the options.
upvoted 0 times
...
Herminia
4 months ago
I feel like it might be when you deliver a sales order, but I need to double-check my notes on that.
upvoted 0 times
...
Vannessa
4 months ago
I remember a similar question where we discussed MRP results, but I can't recall if that was the right moment for consumption.
upvoted 0 times
...
Benedict
5 months ago
I think consumption of planned independent requirements happens when you create a sales order, but I'm not entirely sure.
upvoted 0 times
...
Daren
5 months ago
Ah, I think I've got it! The consumption of planned independent requirements happens when you create a sales order, because that's when the system actually pulls from the planned inventory to fulfill the customer's demand. The other options don't seem to fit as well.
upvoted 0 times
...
Corazon
5 months ago
I feel pretty confident about this one. I believe the consumption of planned independent requirements takes place when the MRP results are saved, since that's when the system determines the actual demand and creates the planned orders accordingly.
upvoted 0 times
...
Melissa
5 months ago
Okay, let me see. I know that planned orders are created based on MRP, so I'm guessing the consumption happens when those planned orders are created. But I'm not 100% sure, so I'll need to double-check my understanding.
upvoted 0 times
...
Virgie
5 months ago
Hmm, this seems like a tricky one. I'll need to think carefully about the different stages of the planning process and when consumption of independent requirements occurs.
upvoted 0 times
...
Isidra
5 months ago
I'm a bit confused by the wording of the question. Is it asking about when the consumption happens, or when the planned independent requirements are actually used? I'll need to re-read the question carefully to make sure I understand what it's asking.
upvoted 0 times
...
Karima
5 months ago
I'm pretty confident I know the answer to this one. The 5G NSA Option 3x architecture supports MCG_ONLY, SCG_AND_MCG (static), and SCG_AND_MCG (dynamic) data split modes on the gNodeB side.
upvoted 0 times
...
Socorro
5 months ago
I'm pretty sure that a 90% learning curve means you're learning faster than an 80% one, but I had some confusion about the definitions during practice.
upvoted 0 times
...
Louis
5 months ago
I'm a bit confused by this question. The differences between Exceptions and Marked Time aren't entirely clear to me. I'll need to review my notes and maybe ask the instructor for some clarification before I can answer this one.
upvoted 0 times
...
Yolande
10 months ago
Okay, let me think this through... Aha! D is the answer. Creating a planned order triggers the consumption of planned independent requirements. Easy peasy!
upvoted 0 times
Vallie
9 months ago
Great job figuring that out!
upvoted 0 times
...
Asha
9 months ago
Got it, thanks for clarifying!
upvoted 0 times
...
Jeanice
9 months ago
Yes, that's correct. Creating a planned order triggers the consumption of planned independent requirements.
upvoted 0 times
...
Jamika
9 months ago
Yes, that's correct. Creating a planned order triggers the consumption of planned independent requirements.
upvoted 0 times
...
Nieves
10 months ago
I think it's when you create a planned order.
upvoted 0 times
...
Ronna
10 months ago
I think it's when you create a planned order.
upvoted 0 times
...
...
Laura
10 months ago
Haha, I was totally off. I thought it was A, when you deliver a sales order. Guess I need to brush up on my planning strategy 40 knowledge!
upvoted 0 times
...
Aileen
10 months ago
This one's tricky, but I think the correct answer is C. When you create a sales order, that's when the consumption happens. Am I right?
upvoted 0 times
...
Shelia
10 months ago
Ah, I was thinking it was B. When the MRP results are saved, that's when the consumption happens. But I guess D makes more sense.
upvoted 0 times
Isadora
8 months ago
Glory: That's right, it's when you create a planned order.
upvoted 0 times
...
Deeanna
9 months ago
User 3: So it's when you create a planned order then?
upvoted 0 times
...
Glory
9 months ago
User 2: Yeah, creating a planned order makes more sense for consumption.
upvoted 0 times
...
James
10 months ago
User 1: I thought it was B too, but D does make more sense.
upvoted 0 times
...
...
Leslie
10 months ago
Hmm, I'd say the answer is D. When you create a planned order, that's when the consumption of planned independent requirements takes place.
upvoted 0 times
...
Deangelo
10 months ago
I'm not sure, but I think it might be when the MRP results are saved. Can someone confirm?
upvoted 0 times
...
Donette
11 months ago
I agree with Eva. When you create a planned order, that's when the consumption happens.
upvoted 0 times
...
Eva
11 months ago
I think the consumption of planned independent requirements takes place when you create a planned order.
upvoted 0 times
...