SAP Exam C_TS412_1909 Topic 1 Question 13 Discussion

Actual exam question for SAP's C_TS412_1909 exam
Question #: 13
Topic #: 1
[All C_TS412_1909 Questions]

Materials

Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set

of dates that can be scheduled.

Which set of dates can be used for scheduled for network?

Note : there are 2 correct answer for this question.

Show Suggested Answer Hide Answer
Suggested Answer: C, E