SAP Exam C_TS410_2504 Topic 2 Question 9 Discussion

Actual exam question for SAP's C_TS410_2504 exam
Question #: 9
Topic #: 2
[All C_TS410_2504 Questions]

What occurs when planning an internal project activity?

Show Suggested Answer Hide Answer
Suggested Answer: C

Project Planning and Activities: When planning activities for internal projects in SAP, resources, materials, and services required for the project are identified.

Generating Purchase Requisitions:

Automated Procurement: As part of the planning process, the system can automatically generate purchase requisitions for the materials and services needed for the project activities.

Integration with Materials Management: These purchase requisitions can then be processed in the Materials Management (MM) module to procure the required resources.

Implementation Steps:

Project Planning: In the Project System (PS) module, plan the project activities and define the resources required.

Requisition Generation: Ensure that the system is set up to automatically generate purchase requisitions based on the project planning data.


SAP Project System Configuration Guide

SAP Materials Management (MM) Documentation