A user is assigned a curriculum with an item having the following configuration: initial assignment of 30 days; initial basis: event; an assignment date of October 16th, 2021. What would the User's calculated required date be?
Correct! The User's calculated required date would be November 15th, 2021, based on the initial assignment of 30 days from the assignment date of October 16th, 2021.