Hmm, this one's tricky. I'm leaning towards Option C, since we need to add a Machine resource for the calibration machine and a forecast for the technician. That way, we can estimate the capacity needed for both.
Option D seems like the easiest way to go. Adding an item master data for the machine and an employee master data for the technician should give us the information we need to plan capacity.
I think Option B is the correct answer. The production process requires both machine and labor resources, so we need to define a Machine resource for the calibration machine and a Labor resource for the technician employee.