Which of the following are captured in a completed Digital Discovery Assessment?Note: There are 2 Correct Answe rs to this questio n.
Solution:
Here are the two elements captured in a completed Digital Discovery Assessment, based on learning.sap.com:
Correct Answe rs
A . Target customer go-live date
* During the Detailed Discovery phase of the DDA, project and scope questions are completed---including the customer's target go-live date---as part of the decision-making and handover information. Passquestio n.com+15learning.sap.com+15learning.sap.com+15
D . Known integration requirements
* The DDA captures known integrations (systems the customer plans to connect), ensuring these are included in the implementation scope handed over to the team. learning.sap.com+3learning.sap.com+3quizlet.com+3
Incorrect Options
* B. SAP Fiori application extensions are not part of the DDA---they're uncovered later during Fit-to-Standard.
* C. Business role permission requirements aren't captured in the DDA; these are scoped during realization or workshop phases.
Final Selection:
* A. Target customer go-live date
* D. Known integration requirements