SAP Exam C_S43_2022 Topic 2 Question 17 Discussion

Actual exam question for SAP's C_S43_2022 exam
Question #: 17
Topic #: 2
[All C_S43_2022 Questions]

What can be determined using the offset within a maintenance strategy? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A, B, E

Contribute your Thoughts:

Carin
21 hours ago
A one-time shift of a maintenance package? That sounds like my morning commute!
upvoted 0 times
...
Gianna
6 days ago
Offset? More like 'off-putting'! I just hope the real exam doesn't have too many tricky questions like this one.
upvoted 0 times
...
Martina
8 days ago
The offset is all about timing, so I'm guessing the call date for the maintenance order is also something it can determine. But I could be wrong on that one.
upvoted 0 times
...
Basilia
13 days ago
Hmm, I'm not sure about the preliminary buffer shifting the reference date. Seems a bit too specific to me. I'll go with A and B.
upvoted 0 times
...
Junita
16 days ago
I believe the offset can help in determining the call date for the maintenance order as well. It's important for scheduling purposes.
upvoted 0 times
...
Mi
17 days ago
The offset can determine the first due date of a maintenance package and a one-time shift of a maintenance package. I'm pretty sure those are the correct answers here.
upvoted 0 times
...
Venita
18 days ago
I agree with Sage. The offset can also be used to shift the reference date of the maintenance order.
upvoted 0 times
...
Sage
22 days ago
I think the offset can determine the first due date of a maintenance package.
upvoted 0 times
...