SAP Exam C_IBP_2311 Topic 4 Question 33 Discussion

Actual exam question for SAP's C_IBP_2311 exam
Question #: 33
Topic #: 4
[All C_IBP_2311 Questions]

You create a planning filter using an SAP IBP Fiori app. Which of the following objects can it be appliedto? Note: There are 2 correct answers to this question.

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Ty
2 months ago
This question is like a riddle wrapped in an enigma. I feel like I need to consult the Oracle of Supply Chain Management to answer this one.
upvoted 0 times
Kimi
28 days ago
B) Use production lead times and offsets to manage components at the outsourced manufacturing location
upvoted 0 times
...
Felicia
1 months ago
A) Model relative production costs across internal locations and outsourced manufacturing locations
upvoted 0 times
...
...
Lino
2 months ago
Hold up, why do we need a separate subnetwork for the outsourced locations? Isn't that just making things more complicated than necessary?
upvoted 0 times
Sherita
1 months ago
B) Use production lead times and offsets to manage components at the outsourced manufacturing location
upvoted 0 times
...
Temeka
1 months ago
A) Model relative production costs across internal locations and outsourced manufacturing locations
upvoted 0 times
...
...
Daron
2 months ago
Hmm, I'm not so sure. Modeling relative production costs and target inventory at the outsourced locations also seem important. This is a tough one!
upvoted 0 times
...
Pearline
2 months ago
I agree with Aretha. The question is specifically asking about prerequisites, and option B seems to cover that the best.
upvoted 0 times
An
21 days ago
D) Model target inventory and stocks at the outsourced manufacturing location
upvoted 0 times
...
Patti
22 days ago
C) Ensure that the outsourced manufacturing locations have a separate subnetwork
upvoted 0 times
...
Bettina
1 months ago
B) Use production lead times and offsets to manage components at the outsourced manufacturing location
upvoted 0 times
...
Ty
1 months ago
A) Model relative production costs across internal locations and outsourced manufacturing locations
upvoted 0 times
...
...
Corrinne
2 months ago
I still think A) is the best option, but B) could also play a role in optimizing supply.
upvoted 0 times
...
Frederica
2 months ago
That's a good point, Gladys. It's important to consider lead times as well.
upvoted 0 times
...
Aretha
2 months ago
Option B is the correct answer. Managing components at the outsourced manufacturing location is crucial for the Supply Optimizer to work effectively.
upvoted 0 times
Margret
27 days ago
D) Model target inventory and stocks at the outsourced manufacturing location
upvoted 0 times
...
Jean
30 days ago
C) Ensure that the outsourced manufacturing locations have a separate subnetwork
upvoted 0 times
...
Corrie
1 months ago
B) Use production lead times and offsets to manage components at the outsourced manufacturing location
upvoted 0 times
...
Silvana
2 months ago
A) Model relative production costs across internal locations and outsourced manufacturing locations
upvoted 0 times
...
...
Gladys
3 months ago
But what about B) Use production lead times and offsets? That could also be important for managing components.
upvoted 0 times
...
Corrinne
3 months ago
I agree with Frederica, it makes sense to compare production costs to optimize supply.
upvoted 0 times
...
Frederica
3 months ago
I think the answer is A) Model relative production costs across internal locations and outsourced manufacturing locations.
upvoted 0 times
...

Save Cancel