What Planning Strategies Should be Taken to Make User Acceptance Testing (UAT) efficient?
Efficient UAT requires:
B -- Define acceptance criteria upfront
D -- Train UAT testers on new Revenue Cloud processes and CPQ/Billing functionality
E -- Finalize test plans before build phase completes to ensure readiness
Options A and C are incorrect:
Consultants should NOT execute tests for the customer (UAT = customer validation).
Not every issue in UAT is a change request; many are defects that must be fixed.
All answers you provided are confirmed correct based on Salesforce CPQ & Billing documentation and implementation methodology.