Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
Suggested Answer: C
Get Premium PRINCE2-Foundation Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
13 comments · newest first
AL
Albert
1 year ago
I’m not sure about this one, feels tricky!
LO
Lorenza
1 year ago
"Capture" is just about logging issues, right?
TR
Tresa
1 year ago
Wait, is it really "Decide"? That seems off.
RH
Rhea
1 year ago
Nah, I believe it's "Propose."
AN
An
1 year ago
I think it's definitely "Examine."
RO
Ronald
1 year ago
I’m leaning towards "Capture" because it sounds like it would involve gathering information, but I could be mixing it up with another concept.
CH
Chery
1 year ago
I feel like "Decide" could also be relevant, but it seems more about making a choice rather than exploring options.
GR
Graciela
1 year ago
I remember practicing a question like this, and I think "Propose" might be the right answer since it involves suggesting different responses.
AL
Alysa
1 year ago
I think the step that considers alternative options is "Examine," but I'm not entirely sure.
BO
Bobbye
1 year ago
This question seems straightforward, I think the recommended practice is to use a VDI advanced policy.
SE
Sena
1 year ago
Hmm, this looks like a tricky one. I'll need to carefully read through the options and make sure I understand the requirements before selecting an answer.
KR
Kris
1 year ago
Hmm, this seems straightforward. A performance-based contract is all about the speed of execution, so I'm going to go with True on this one.
AM
Amie
1 year ago
Synchronizing directories doesn't seem like it would be the first step, so I'm leaning towards option D.