PRINCE2-Foundation Exam - Topic 5 Question 65 Discussion

Which is a minimum requirement for applying the plans theme?
C) Scope tolerance must be prioritized using MoSCoW
A) The project must have at least two management stages
B) The team managers in the project must prepare team plans
D) The project plan must be presented as a Gantt chart

PRINCE2-Foundation Exam - Topic 5 Question 65 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 65
Topic #: 5
[All PRINCE2-Foundation Questions]

Which is a minimum requirement for applying the plans theme?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Lina
7 months ago
Not sure if two management stages are enough...
upvoted 0 times
...
Ryann
7 months ago
MoSCoW prioritization is key, no doubt!
upvoted 0 times
...
Julio
7 months ago
Wait, do we really need a Gantt chart for every project?
upvoted 0 times
...
Ty
7 months ago
I think B is more important!
upvoted 0 times
...
Sonia
8 months ago
A is definitely a requirement.
upvoted 0 times
...
Shawn
8 months ago
I practiced a question about project plans needing to be in a Gantt chart format, but I don't think that's a minimum requirement for applying the plans theme.
upvoted 0 times
...
Cristy
8 months ago
I feel like the MoSCoW method is important for prioritizing scope, but I don't know if it's specifically tied to the plans theme.
upvoted 0 times
...
Carri
8 months ago
I remember something about team managers needing to prepare plans, but I can't recall if that's a minimum requirement or just a good practice.
upvoted 0 times
...
Sherell
8 months ago
I think the plans theme requires at least two management stages, but I'm not completely sure if that's the only requirement.
upvoted 0 times
...
Shawnta
8 months ago
This question seems pretty straightforward. I think the answer is A - True.
upvoted 0 times
...
Latanya
8 months ago
This seems like a straightforward question. I think the Microsoft 365 admin center or the Microsoft 365 Roadmap would be the best options to find information on the release dates of new features.
upvoted 0 times
...
Luz
9 months ago
I'm a bit confused by the wording of these options. I'll need to re-read them carefully to make sure I don't miss any important nuances.
upvoted 0 times
...
Whitley
9 months ago
I think we practiced something like this in class. Blocking PSTN patterns might help reduce unnecessary call transfers.
upvoted 0 times
...
Florinda
1 year ago
Wait, so the plans theme is all about Gantt charts now? I thought we were living in the 21st century!
upvoted 0 times
...
Lenna
1 year ago
Haha, a Gantt chart? I thought we were done with those back in the 90s. Definitely not a minimum requirement!
upvoted 0 times
Lenna
12 months ago
C) Scope tolerance must be prioritized using MoSCoW
upvoted 0 times
...
Monroe
1 year ago
B) The team managers in the project must prepare team plans
upvoted 0 times
...
Reta
1 year ago
C) Scope tolerance must be prioritized using MoSCoW
upvoted 0 times
...
Valentin
1 year ago
A) The project must have at least two management stages
upvoted 0 times
...
Louis
1 year ago
B) The team managers in the project must prepare team plans
upvoted 0 times
...
Madonna
1 year ago
A) The project must have at least two management stages
upvoted 0 times
...
...
Lawana
1 year ago
I disagree with option C. MoSCoW is a prioritization technique, but it's not a minimum requirement for the plans theme.
upvoted 0 times
...
Hubert
1 year ago
I'm not sure about that. Isn't the plans theme more about the overall project plan, rather than just the team plans?
upvoted 0 times
Shawna
12 months ago
D) The project plan must be presented as a Gantt chart
upvoted 0 times
...
Helga
12 months ago
C) Scope tolerance must be prioritized using MoSCoW
upvoted 0 times
...
Anisha
12 months ago
B) The team managers in the project must prepare team plans
upvoted 0 times
...
Sherron
12 months ago
A) The project must have at least two management stages
upvoted 0 times
...
Joana
12 months ago
D) The project plan must be presented as a Gantt chart
upvoted 0 times
...
Filiberto
12 months ago
C) Scope tolerance must be prioritized using MoSCoW
upvoted 0 times
...
Ozell
1 year ago
B) The team managers in the project must prepare team plans
upvoted 0 times
...
Helga
1 year ago
A) The project must have at least two management stages
upvoted 0 times
...
...
Blondell
1 year ago
I think option A is the correct answer, as having at least two management stages is a fundamental requirement for applying the plans theme.
upvoted 0 times
...
Ellsworth
1 year ago
But don't you think scope tolerance should be prioritized using MoSCoW?
upvoted 0 times
...
Cristal
1 year ago
I disagree, I believe the team managers in the project must prepare team plans.
upvoted 0 times
...
Ellsworth
1 year ago
I think the minimum requirement is that the project must have at least two management stages.
upvoted 0 times
...
Brittani
1 year ago
Hmm, that makes sense too. Maybe it's a combination of both A) and C) then.
upvoted 0 times
...
Catrice
1 year ago
I disagree, I believe it's C) Scope tolerance must be prioritized using MoSCoW.
upvoted 0 times
...
Brittani
1 year ago
I think the minimum requirement is A) The project must have at least two management stages.
upvoted 0 times
...

Save Cancel