Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2-Foundation Exam - Topic 4 Question 92 Discussion

Which statement defines a risk?
C) An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
A) A certain event occurring in the future that will have a negative impact on the project's objectives
B) An event that has already occurred that the Project Manager must deal with immediately
D) An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response

PRINCE2-Foundation Exam - Topic 4 Question 92 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 92
Topic #: 4
[All PRINCE2-Foundation Questions]

Which statement defines a risk?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Aliza
6 months ago
D sounds too specific. Risks aren't always escalated, right?
upvoted 0 times
...
Cordie
7 months ago
Totally with you on C! Makes the most sense.
upvoted 0 times
...
Karl
7 months ago
Wait, so B isn't a risk? That seems off.
upvoted 0 times
...
Quentin
7 months ago
I think A is misleading. Risks aren't always negative.
upvoted 0 times
...
Lore
7 months ago
Definitely C! It's all about uncertainty.
upvoted 0 times
...
Aleshia
8 months ago
I feel like B is definitely wrong since it talks about events that have already happened. That doesn’t fit the definition of a risk at all.
upvoted 0 times
...
Cassi
8 months ago
I’m confused between C and D. C sounds right, but D mentions escalation, which seems more about response rather than defining risk.
upvoted 0 times
...
Julio
8 months ago
I remember practicing a question similar to this, and I think risks are about potential future events, which makes me think A might be too definitive.
upvoted 0 times
...
Carissa
8 months ago
I think a risk is something uncertain, so I’m leaning towards C, but I’m not completely sure.
upvoted 0 times
...
Maybelle
8 months ago
I've got a good feeling about option C. That definition really captures the essence of what a risk is - an uncertain event that could affect the project's goals. I'm confident that's the right answer.
upvoted 0 times
...
Edda
8 months ago
I'm a bit confused on this one. Are we looking for the definition of a risk, or something else? I want to make sure I understand the question before I answer.
upvoted 0 times
...
Darci
8 months ago
Okay, let's see here. A risk is an uncertain event that could have a negative impact, so I'm going to go with option C. Seems like the most comprehensive definition to me.
upvoted 0 times
...
Paul
8 months ago
Hmm, I'm a little unsure about this one. I was thinking option A might be the right answer, but now I'm not so sure. I'll have to think it through a bit more.
upvoted 0 times
...
Gail
8 months ago
This one seems pretty straightforward. I think option C is the best definition of a risk - an uncertain event that could affect the project's objectives.
upvoted 0 times
...
Danilo
1 year ago
Hmm, C seems like the obvious choice, but I'm still chuckling at the mental image of a project manager frantically dealing with events that have already occurred. That's a whole other level of risk management!
upvoted 0 times
...
Herschel
1 year ago
C is the way to go. Risks are all about uncertain future events, not things that have already happened or are auTraceyatically escalated.
upvoted 0 times
Herman
11 months ago
I always thought risks were events that had already occurred, but now I see that C makes more sense.
upvoted 0 times
...
Margot
12 months ago
C is the best option, it captures the essence of what a risk is.
upvoted 0 times
...
Lilli
12 months ago
Definitely, risks are all about uncertain future events.
upvoted 0 times
...
Annette
1 year ago
I agree, C is the correct definition of a risk.
upvoted 0 times
...
...
Tracey
1 year ago
I was torn between B and C, but C is the most comprehensive description of a risk. The other choices are too narrow in scope.
upvoted 0 times
Wenona
12 months ago
User 3: Definitely, C is the most comprehensive definition of a risk.
upvoted 0 times
...
Maia
1 year ago
User 2: I agree, B is too specific and A and D are not accurate.
upvoted 0 times
...
Lino
1 year ago
User 1: I think C is the best choice, it covers all possibilities.
upvoted 0 times
...
...
Dana
1 year ago
I agree, C is the best definition of a risk. The other options don't fully capture the essence of what a risk is in project management.
upvoted 0 times
Tamie
1 year ago
C is the one that makes the most sense to me.
upvoted 0 times
...
Eden
1 year ago
Definitely, C is the most accurate definition.
upvoted 0 times
...
Loise
1 year ago
I agree, C is the best definition of a risk.
upvoted 0 times
...
Trinidad
1 year ago
I think C is the correct answer.
upvoted 0 times
...
...
Lorriane
1 year ago
I believe the answer is A, as it mentions a negative impact on project objectives.
upvoted 0 times
...
Reuben
1 year ago
Option C definitely seems like the correct answer here. The key is the uncertainty of the event and its potential impact on the project objectives.
upvoted 0 times
Cristal
1 year ago
It's important to identify and plan for those potential risks.
upvoted 0 times
...
Yolando
1 year ago
Definitely, we need to be prepared for those uncertain events.
upvoted 0 times
...
Macy
1 year ago
User 2: Yeah, it's all about those uncertain events that could affect our objectives.
upvoted 0 times
...
Lenora
1 year ago
I think so too, it's all about the uncertainty and potential impact.
upvoted 0 times
...
Caitlin
1 year ago
User 1: I agree, option C is the best definition of a risk.
upvoted 0 times
...
Inocencia
1 year ago
I agree, option C is the best definition of a risk.
upvoted 0 times
...
...
Leatha
1 year ago
I agree with Freeman, because a risk is an uncertain event that could affect objectives.
upvoted 0 times
...
Freeman
1 year ago
I think the answer is C.
upvoted 0 times
...

Save Cancel