Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PRINCE2 Exam PRINCE2-Foundation Topic 2 Question 84 Discussion

Actual exam question for PRINCE2's PRINCE2-Foundation exam
Question #: 84
Topic #: 2
[All PRINCE2-Foundation Questions]

When should the Project Board refer to corporate or programme management for a decision?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Carlota
13 days ago
Wait, is this a trick question? The correct answer is obviously E) All of the above. When in doubt, always go with the 'all of the above' option!
upvoted 0 times
...
Terrilyn
14 days ago
Option A is the answer, right? I mean, if the stage requires additional resources, the Project Board would need to consult with the big bosses to get that approved.
upvoted 0 times
...
Nichelle
16 days ago
I'm going with Option C. If the Senior Supplier or Senior User needs to be changed, that's a big decision that the Project Board can't make on their own.
upvoted 0 times
...
Loren
18 days ago
I think Option D is the way to go. Any change request should be approved by the appropriate authorities, so that's when the Project Board should seek guidance from the higher-ups.
upvoted 0 times
Ronny
2 days ago
A) The stage requires resources
upvoted 0 times
...
...
Lea
1 months ago
Option B seems like the obvious choice here. If the project is forecasted to exceed its tolerance levels, the Project Board should definitely refer to higher management for a decision.
upvoted 0 times
Twanna
8 days ago
B: Agreed, it's important to involve corporate or programme management when there's a risk of exceeding tolerance.
upvoted 0 times
...
Lawanda
9 days ago
A: I think option B is the right choice. If the project is going to exceed its tolerance levels, we need to refer to higher management.
upvoted 0 times
...
...
Rolland
2 months ago
I believe that referring to corporate or programme management is also necessary when there is a forecast that project level tolerance will be exceeded. It's crucial to manage risks effectively.
upvoted 0 times
...
Avery
2 months ago
I agree with Jettie. It's important to involve higher management when additional resources are needed to ensure alignment with overall objectives.
upvoted 0 times
...
Jettie
2 months ago
I think the Project Board should refer to corporate or programme management when the stage requires resources.
upvoted 0 times
...

Save Cancel