Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Simona
3 days ago
I'm not sure, but I think it could also be A) Risk category, as categorizing risks is important in managing them.
upvoted 0 times
...
Laura
4 days ago
I agree with Josephine, because risk response involves taking actions to address risks.
upvoted 0 times
...
Josephine
7 days ago
I think the answer is C) Risk response.