PRINCE2-Agile-Foundation Exam - Topic 4 Question 66 Discussion

Posted by Carolann on Jan 09, 2025 at 10:32 AM

Which statement defines a PRINCE2 principle?

Suggested Answer: B

Get Premium PRINCE2-Agile-Foundation Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
26 comments · newest first
NA
Nakisha 11 months ago
Not sure about D, that doesn't sound like a core principle to me.
KA
Kassandra 12 months ago
Totally agree with B! It's all about that stage control.
JO
Joesph 12 months ago
Wait, is tailoring to the competitor's environment really a principle? Sounds off.
CH
Chun 1 year ago
I think option C is the best choice here.
ZO
Zoila 1 year ago
A PRINCE2 project is definitely monitored stage-by-stage!
BE
Bernardo 1 year ago
I remember discussing risk management in relation to PRINCE2, so option C could be the right choice, but I need to double-check my notes.
KE
Keneth 1 year ago
I thought a key principle was about tailoring the project to the environment, so option D might be correct, but I’m not completely confident.
EM
Emerson 1 year ago
I feel like option B sounds familiar because we talked about stage monitoring in our practice questions, but I can't recall if it's a principle or just a process.
BA
Barb 1 year ago
I think I remember that PRINCE2 has principles about quality and risk management, but I'm not sure which one is the right answer here.
VI
Virgie 1 year ago
Ugh, PRINCE2 principles are not my strong suit. I'll have to make an educated guess on this one and hope for the best.
RO
Rossana 1 year ago
Okay, I remember learning about the PRINCE2 principles in class. I think the key here is to identify which one of these statements best captures a core principle.
JO
Jolanda 1 year ago
Hmm, I'm not totally sure about the PRINCE2 principles. Let me think this through carefully and see if I can eliminate some of the options.
LI
Lili 1 year ago
This looks like a straightforward PRINCE2 question. I'm pretty confident I know the principles, so I'll review them quickly before answering.
CY
Cyril 2 years ago
Hmm, I'm going with option B. Stagewise management is a fundamental PRINCE2 principle, unlike that 'competitor' nonsense in option D.
AN
Annabelle 2 years ago
Option A sounds good, but it's not a PRINCE2 principle. Quality management is part of the PRINCE2 method, not a principle.
FR
Francoise 2 years ago
Definitely not option D. PRINCE2 is tailored to the project environment, not the competitor's environment. Silly answer!
MO
Mozell 2 years ago
↳ replying to Francoise
C) A PRINCE2 project ensures a consistent approach to risk management
CO
Cortney 2 years ago
↳ replying to Francoise
B) A PRINCE2 project is monitored and controlled on a stage-by-stage basis
CH
Chantell 2 years ago
↳ replying to Francoise
A) A PRINCE2 project defines its quality management approach
SE
Sena 2 years ago
I think option C is the right choice. Consistent risk management is a key principle of PRINCE2.
BA
Barney 2 years ago
Option B is the correct answer. A PRINCE2 project is indeed monitored and controlled on a stage-by-stage basis.
MI
Millie 2 years ago
↳ replying to Barney
Yes, you're right. That's one of the key principles of PRINCE2.
DO
Dona 2 years ago
↳ replying to Barney
I think option B is correct. A PRINCE2 project is monitored and controlled on a stage-by-stage basis.
CO
Corinne 2 years ago
I'm not sure, but I think D) A PRINCE2 project is tailored to suit the competitor's environment could also be a valid answer.
GA
Gabriele 2 years ago
I agree with Hoa. It makes sense to have a consistent approach to risk management in a project.
HO
Hoa 2 years ago
I think the answer is C) A PRINCE2 project ensures a consistent approach to risk management.