PRINCE2-Agile-Foundation Exam - Topic 1 Question 45 Discussion

What needs to happen when new detailed requirements are added to a timebox?
C) The delivery milestones should be reviewed and re-planned
A) Requirements of a similar level of effort should be removed
B) More people should be added to the delivery team
D) Formal change control should be applied

PRINCE2-Agile-Foundation Exam - Topic 1 Question 45 Discussion

Actual exam question for PRINCE2's PRINCE2-Agile-Foundation exam
Question #: 45
Topic #: 1
[All PRINCE2-Agile-Foundation Questions]

What needs to happen when new detailed requirements are added to a timebox?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

0/2000 characters
Shizue
6 months ago
Reviewing and re-planning milestones is a must in this case.
upvoted 0 times
...
Helga
7 months ago
Wait, are we really supposed to remove existing requirements? That seems risky!
upvoted 0 times
...
Argelia
7 months ago
I think we should just add more people instead.
upvoted 0 times
...
Miss
7 months ago
Totally agree, can't overload the team!
upvoted 0 times
...
Zita
7 months ago
Requirements of a similar level of effort should be removed.
upvoted 0 times
...
Gladys
8 months ago
Adding more people to the team seems like it could help, but I feel like it might complicate things instead of solving them.
upvoted 0 times
...
Kayleigh
8 months ago
I'm leaning towards the idea of applying formal change control, but I wonder if that’s necessary for every new requirement added.
upvoted 0 times
...
Sina
8 months ago
I remember a practice question that mentioned reviewing delivery milestones when changes happen. That seems relevant here.
upvoted 0 times
...
Rashida
8 months ago
I think when new requirements come in, we might need to remove some existing ones, but I'm not entirely sure if that's always the case.
upvoted 0 times
...
Julie
8 months ago
Ah, this is the kind of question I was hoping to see. I've got a good strategy for this.
upvoted 0 times
...
Daniel
8 months ago
Okay, I think I know the right approach here. Let me jot down my thoughts.
upvoted 0 times
...
Adelina
8 months ago
Hmm, I'm not totally sure about this. I'll have to review the material on timebox management again.
upvoted 0 times
...
Lindy
8 months ago
This seems like a tricky one. I'll need to think through the options carefully.
upvoted 0 times
...
Skye
8 months ago
This one seems pretty straightforward. I'm pretty sure the max distance for 1 Gbps Ethernet with Cat 6 is 100 meters.
upvoted 0 times
...
Jillian
1 year ago
Don't forget to add more people to the team. That's the only way to get more work done, right? (Wink, wink)
upvoted 0 times
Yuette
1 year ago
D) Formal change control should be applied
upvoted 0 times
...
Nida
1 year ago
C) The delivery milestones should be reviewed and re-planned
upvoted 0 times
...
Darnell
1 year ago
A) Requirements of a similar level of effort should be removed
upvoted 0 times
...
...
Luis
1 year ago
Formal change control, as mentioned in option D, is also important to document the changes and ensure everyone is on the same page.
upvoted 0 times
...
Wava
1 year ago
I believe formal change control should be applied to ensure proper documentation and approval.
upvoted 0 times
...
Douglass
1 year ago
I agree with Quiana. Adjusting the milestones is crucial to ensure the project stays on track with the new requirements.
upvoted 0 times
Tyisha
1 year ago
I think adjusting the milestones is necessary to make sure we can still meet the project deadlines.
upvoted 0 times
...
Junita
1 year ago
Yes, I agree. It's important to review and re-plan the delivery milestones when new requirements are added.
upvoted 0 times
...
Ronald
1 year ago
D) Formal change control should be applied
upvoted 0 times
...
Sarah
1 year ago
C) The delivery milestones should be reviewed and re-planned
upvoted 0 times
...
Shenika
1 year ago
A) Requirements of a similar level of effort should be removed
upvoted 0 times
...
...
Hubert
1 year ago
I agree with Lettie, it's important to adjust the plan when new requirements are added.
upvoted 0 times
...
Quiana
1 year ago
Option C seems like the most reasonable approach. Reviewing and re-planning the delivery milestones seems like the best way to accommodate the new requirements.
upvoted 0 times
...
Lettie
1 year ago
I think the delivery milestones should be reviewed and re-planned.
upvoted 0 times
...

Save Cancel