What needs to happen when new detailed requirements are added to a timebox?
Suggested Answer: C
Get Premium PRINCE2-Agile-Foundation Questions
as Interactive Web-Based Practice Test or PDF
Real Exam Format
Detailed Explanations
Instant Access
Get Your Practice Test
29 comments · newest first
SH
Shizue
11 months ago
Reviewing and re-planning milestones is a must in this case.
HE
Helga
12 months ago
Wait, are we really supposed to remove existing requirements? That seems risky!
AR
Argelia
12 months ago
I think we should just add more people instead.
MI
Miss
1 year ago
Totally agree, can't overload the team!
ZI
Zita
1 year ago
Requirements of a similar level of effort should be removed.
GL
Gladys
1 year ago
Adding more people to the team seems like it could help, but I feel like it might complicate things instead of solving them.
KA
Kayleigh
1 year ago
I'm leaning towards the idea of applying formal change control, but I wonder if that’s necessary for every new requirement added.
SI
Sina
1 year ago
I remember a practice question that mentioned reviewing delivery milestones when changes happen. That seems relevant here.
RA
Rashida
1 year ago
I think when new requirements come in, we might need to remove some existing ones, but I'm not entirely sure if that's always the case.
JU
Julie
1 year ago
Ah, this is the kind of question I was hoping to see. I've got a good strategy for this.
DA
Daniel
1 year ago
Okay, I think I know the right approach here. Let me jot down my thoughts.
AD
Adelina
1 year ago
Hmm, I'm not totally sure about this. I'll have to review the material on timebox management again.
LI
Lindy
1 year ago
This seems like a tricky one. I'll need to think through the options carefully.
SK
Skye
1 year ago
This one seems pretty straightforward. I'm pretty sure the max distance for 1 Gbps Ethernet with Cat 6 is 100 meters.
JI
Jillian
2 years ago
Don't forget to add more people to the team. That's the only way to get more work done, right? (Wink, wink)
YU
Yuette
1 year ago
D) Formal change control should be applied
NI
Nida
1 year ago
C) The delivery milestones should be reviewed and re-planned
DA
Darnell
1 year ago
A) Requirements of a similar level of effort should be removed
LU
Luis
2 years ago
Formal change control, as mentioned in option D, is also important to document the changes and ensure everyone is on the same page.
WA
Wava
2 years ago
I believe formal change control should be applied to ensure proper documentation and approval.
DO
Douglass
2 years ago
I agree with Quiana. Adjusting the milestones is crucial to ensure the project stays on track with the new requirements.
TY
Tyisha
2 years ago
I think adjusting the milestones is necessary to make sure we can still meet the project deadlines.
JU
Junita
2 years ago
Yes, I agree. It's important to review and re-plan the delivery milestones when new requirements are added.
RO
Ronald
2 years ago
D) Formal change control should be applied
SA
Sarah
2 years ago
C) The delivery milestones should be reviewed and re-planned
SH
Shenika
2 years ago
A) Requirements of a similar level of effort should be removed
HU
Hubert
2 years ago
I agree with Lettie, it's important to adjust the plan when new requirements are added.
QU
Quiana
2 years ago
Option C seems like the most reasonable approach. Reviewing and re-planning the delivery milestones seems like the best way to accommodate the new requirements.
LE
Lettie
2 years ago
I think the delivery milestones should be reviewed and re-planned.