Which is a benefit of the Lean Startup approach to releasing a product?
B) It enables the release plans to be synchronized with the PRINCE2 plans
A) It provide a technique to reduce the testing of a product before release
C) It reduces the number of people needed to manage a release of a product
D) It provides quick feedback that can be responded to at the earliest opportunity