PMI-PMOCP Exam - Topic 3 Question 9 Discussion

In a global financial services company, the PMO recently implemented the "Provide Methodologies and Tools" service to ensure project teams use standardized approaches and tools for project management.What key performance indicators (KPIs) should the PMO professional create to measure the performance of this specific service? (Choose 2)
B) Training hours per employee; Measure the number of hours spent training project teams to use the methodologies and tools, as well as the frequency of workshops or refresher courses provided by the PMO. and D) Tool adoption rate; Measure the percentage of project teams using the standardized methodologies and tools and assess how frequently they access the provided templates, frameworks, and guidelines.
A) Strategic outcomes delivery rate; Measure the percentage of strategic goals achieved through completed projects, considering that the service will directly ensure that the organization meets its broader strategic outcomes.
C) Governance compliance rate; Measure the percentage of projects fully compliant with corporate governance policies, considering the service will directly ensure compliance.

PMI-PMOCP Exam - Topic 3 Question 9 Discussion

Actual exam question for PMI's PMI-PMOCP exam
Question #: 9
Topic #: 3
[All PMI-PMOCP Questions]

In a global financial services company, the PMO recently implemented the "Provide Methodologies and Tools" service to ensure project teams use standardized approaches and tools for project management.

What key performance indicators (KPIs) should the PMO professional create to measure the performance of this specific service? (Choose 2)

Show Suggested Answer Hide Answer
Suggested Answer: B, D

For the 'Provide Methodologies and Tools' service, KPIs must measure both the enablement activities and the actual adoption of the methodologies and tools. PMI-PMOCP recommends measuring training hours per employee (option B) as it reflects investment in capacity-building and skill development, critical to effective tool use.

Additionally, the tool adoption rate (option D) directly measures how widely and frequently project teams utilize the standardized methodologies, templates, and guidelines. High adoption indicates the service is effectively embedded in project execution.

While strategic outcomes delivery (option A) and governance compliance rate (option C) are important portfolio or organizational KPIs, they are broader and influenced by many factors beyond the scope of this specific PMO service.


PMI Project Management Office Certified Professional (PMI-PMOCP) Examination Content Outline, PMI 2021.

PMI-PMOCP Study Guide, Chapter on PMO Performance Measurement and Governance.

Contribute your Thoughts:

0/2000 characters
Felice
2 days ago
I'm a bit unsure about which KPIs to pick. A seems relevant, but I also see the value in measuring training hours.
upvoted 0 times
...