Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-100 Topic 2 Question 79 Discussion

Actual exam question for PMI's PMI-100 exam
Question #: 79
Topic #: 2
[All PMI-100 Questions]

When cost variance is negative and schedule variance is positive, the project is:

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Daryl
9 months ago
I think the correct answer is A, because being under budget is a bigger concern than being behind schedule.
upvoted 0 times
...
Tonette
9 months ago
But positive schedule variance means we are ahead of schedule, so it's a bit confusing.
upvoted 0 times
...
Helga
9 months ago
I agree with Angelyn, negative cost variance means we are spending less than planned.
upvoted 0 times
...
Angelyn
9 months ago
A) under budget and behind schedule.
upvoted 0 times
...
Tomas
9 months ago
I think the correct answer is A, because being under budget is a bigger concern than being behind schedule.
upvoted 0 times
...
Shenika
9 months ago
This question is like a bad dad joke. 'When cost variance is negative and schedule variance is positive, the project is... behind schedule and over budget, of course!' *chuckles*
upvoted 0 times
Rebecka
8 months ago
D) complete; all planned values have been earned.
upvoted 0 times
...
Lucy
8 months ago
C) on schedule.
upvoted 0 times
...
Ethan
8 months ago
B) over budget and ahead of schedule.
upvoted 0 times
...
Micah
9 months ago
A) under budget and behind schedule.
upvoted 0 times
...
...
Lachelle
9 months ago
But positive schedule variance means we are ahead of schedule, so it's a bit confusing.
upvoted 0 times
...
Hector
9 months ago
I agree with Wai, negative cost variance means we are spending less than planned.
upvoted 0 times
...
Ardella
9 months ago
Complete? All planned values earned? No way, this project sounds like a hot mess. I'm going with B, the only logical answer here.
upvoted 0 times
Olga
9 months ago
Yeah, definitely over budget but at least ahead of schedule.
upvoted 0 times
...
Cecilia
9 months ago
I agree, B seems like the most logical choice in this situation.
upvoted 0 times
...
...
Georgeanna
10 months ago
Wait, how can the project be on schedule if the cost is negative and the schedule is positive? That doesn't make sense. I'll go with A.
upvoted 0 times
...
Whitley
10 months ago
Aha! I got this one. When you're over budget but ahead of schedule, that's exactly what option B describes. Easy peasy.
upvoted 0 times
Sunshine
9 months ago
A: Yup, that's correct. It's important to keep an eye on both cost and schedule variances.
upvoted 0 times
...
Emmanuel
9 months ago
B: So, the project is progressing faster than planned but costing more than expected.
upvoted 0 times
...
Bev
9 months ago
A: B) over budget and ahead of schedule.
upvoted 0 times
...
...
Wai
10 months ago
A) under budget and behind schedule.
upvoted 0 times
...
Rebbecca
10 months ago
Hmm, this one's tricky. If the cost is under budget but the schedule is behind, that doesn't sound too good. I'm thinking B is the way to go.
upvoted 0 times
Carri
9 months ago
Exactly, it's important to keep track of both cost and schedule variances.
upvoted 0 times
...
Frank
9 months ago
So, it means the project is not going as planned.
upvoted 0 times
...
Trevor
9 months ago
Yeah, if the cost is over budget but the schedule is ahead, that makes sense.
upvoted 0 times
...
Leontine
9 months ago
I think B is correct too.
upvoted 0 times
...
...

Save Cancel