After Define Activities and Sequence Activities, the next process is:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Derick
12 days ago
You know, I was leaning towards option C, but now I'm second-guessing myself. This is a tough one - they really try to trip you up on these certification exams!
upvoted 0 times
...
Willard
12 days ago
Ha, I was just about to say the same thing as Florinda. This exam is designed to mess with our heads, I swear. I'm going with Estimate Activity Resources, but I'm not feeling too confident about it.
upvoted 0 times
...
Florinda
13 days ago
I agree with Lynsey, Estimate Activity Resources seems like the logical next step. Although, Develop Schedule is also a strong contender. Decisions, decisions!
upvoted 0 times
...
Cristy
14 days ago
Ooh, good point Keena! I think you're right. Estimating the resources has to come next, so I'm going with option A.
upvoted 0 times
Bernardo
4 hours ago
I agree with you, I think it's option A as well.
upvoted 0 times
...
...
Lynsey
14 days ago
I was leaning towards Estimate Activity Resources. It just feels like the natural progression, you know? But I could be wrong, this exam stuff can be so confusing sometimes.
upvoted 0 times
...
Keena
15 days ago
I don't know, you guys. Estimating the activity resources seems like it should come before developing the schedule. How can you build a schedule without knowing what resources you have to work with?
upvoted 0 times
...
Brock
15 days ago
Hmm, this is a tricky one. I think the next step is Estimate Activity Durations, but I'm not 100% sure. What do you guys think?
upvoted 0 times
...
Emelda
16 days ago
I agree with Javier. Once you've defined and sequenced the activities, the next step should be to develop the overall project schedule. Estimating resources and durations can come after that.
upvoted 0 times
...
Javier
18 days ago
Hmm, I'm not so sure. Couldn't you argue that developing the schedule is the next logical step? That seems to make the most sense to me.
upvoted 0 times
...
Marya
20 days ago
I think this is a pretty straightforward question. The next step after defining and sequencing the activities is to estimate the activity durations, so I'm going with option B.
upvoted 0 times
...

Save Cancel