Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-100 Topic 1 Question 60 Discussion

Actual exam question for PMI's PMI-100 exam
Question #: 60
Topic #: 1
[All PMI-100 Questions]

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel