A team has completed the work in their Aeration backlog earlier than expected. There is still three days left of the iteration, what should the team do now?
When a team completes their iteration backlog earlier than expected, the recommended approach in Disciplined Agile is to collaborate with the product owner to pull additional work from the product backlog into the iteration backlog. This approach maintains momentum and ensures that the team continues delivering value without waiting for the next iteration. It promotes agility and maximizes productivity by utilizing any remaining time effectively.
A . Working on non-critical tasks or D. waiting for other groups are not effective uses of the team's time and do not align with agile principles of continuous value delivery.
C . Reporting differences in completion time helps with future planning but does not address the immediate need to continue productive work.
Thus, the correct answer is B. Work with the product owner to pull more work from the product backlog into their iteration backlog.
Clarence
10 months agoJoanne
10 months agoLashanda
10 months agoGracia
10 months agoMeghan
11 months agoQuentin
11 months agoLuke
11 months agoValene
11 months agoJanine
11 months agoBrice
11 months agoMarion
11 months agoCasie
11 months agoAlecia
11 months agoLucina
11 months agoVeronika
2 years agoNan
2 years agoLourdes
1 year agoVictor
1 year agoAnisha
1 year agoDion
2 years agoJanna
1 year agoVicente
1 year agoJanessa
2 years agoLindy
2 years agoYoko
2 years agoMeghan
2 years agoJerry
2 years agoJamal
1 year agoXuan
1 year agoFletcher
2 years agoAmina
2 years agoElenora
2 years agoKeneth
2 years ago