Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PeopleCert Exam 18 Topic 2 Question 24 Discussion

Actual exam question for PeopleCert's IASSC Lean Six Sigma - Yellow Belt exam
Question #: 24
Topic #: 2
[All IASSC Lean Six Sigma - Yellow Belt Questions]

Training cost $2,500 and a project required an initial investment of $23,500. If the project yields monthly savings of $2,500 beginning after 4 months, what is the payback period in months (before money costs and taxes)?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel