Which statements about the Portfolio Office (headed by the Portfolio Manager) are true?

1. It helps to ensure that a consistent approach is applied across the portfolio

2. It prepares the Portfolio Strategy and Delivery Plan

3. It is a temporary structure set up to assist with the delivery of change

4. It provides assurance to senior management on effective delivery of change

Show Suggested Answer Hide Answer
Suggested Answer: A