PECB ISO 21502 Lead Project Manager Exam - Topic 2 Question 5 Discussion

Scenario:Leute is a low-cost airline, headquartered in Wien, Austria. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in-flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.Based on scenario 3, Allison ensured that the size of each work package was longer than 8 hours, but less than 80 hours in order to complete them in 1 to 10 working days. What rule did Allison follow in this case?
B) The 8/80 rule
A) The 1/10 rule
C) The reporting period rule

PECB ISO 21502 Lead Project Manager Exam - Topic 2 Question 5 Discussion

Actual exam question for PECB's ISO 21502 Lead Project Manager exam
Question #: 5
Topic #: 2
[All ISO 21502 Lead Project Manager Questions]

Scenario:

Leute is a low-cost airline, headquartered in Wien, Austri

a. The company aims to offer passengers optimal options regarding its services and gain the lead role among other competitors in the airline industry. Recently, Leute experienced a major drop in revenue due to negative reviews from customers in various online platforms. To increase its profit and enhance customer satisfaction, the company decided to expand its in-flight services by offering entertainment, such as movies, audio books, and games, food for purchase in economy and full meals in premium cabins, and comforts, such as blankets and pillows. For the implementation of this project and future projects of the airline, the CEO of Leute, Michaele Wagner, decided to follow the guidelines of ISO 21502 on project management.

Initially, Allison, the project manager, created a short document in which she justified and summarized all project aspects, including: the nature and purpose of the project, the objectives of the project, key milestones of the project and the time needed to complete the project, and the audience that the project targets.

Afterward, Allison held a meeting with Michaele during which she presented this document and briefly explained each of its points. After a considerable amount of analysis and discussions, the project initiation was approved by Michaele. In addition, a team of eighteen members was authorized to start with the project activities.

While undertaking the project activities, Allison ensured that each work package takes longer than 8 hours, but less than 80 hours, so that they would be completed in 1 to 10 working days. In addition, during this phase, several changes were made in the predefined aspects of the project, which were approved by Nick Todd, the project sponsor. For instance, initially, the project delivery was set to be completed after six months. However, considering how the project was implemented and the time required for the completion of each phase, the deadline for the project completion was postponed for another two months. These changes were also reflected in the business case, which was updated accordingly.

A month after the project execution began, Allison conducted an earned value analysis to measure the progress of the project up to that stage. She measured how efficiently the work was being performed with regard to its budgeted cost, after which she concluded that it was going according to the plan. Moreover, she organized a meeting with relevant project stakeholders in order to communicate the progress report to them.

Based on scenario 3, Allison ensured that the size of each work package was longer than 8 hours, but less than 80 hours in order to complete them in 1 to 10 working days. What rule did Allison follow in this case?

Show Suggested Answer Hide Answer
Suggested Answer: B

The correct answer is B. The 8/80 rule. This rule is used when decomposing work into work packages or activities. It states that a work package should generally require no less than 8 hours and no more than 80 hours of effort. In practical terms, this means the work package should be large enough to avoid excessive administrative fragmentation, but small enough to be estimated, assigned, monitored, and controlled effectively. In Allison's case, she ensured that each work package took longer than 8 hours but less than 80 hours and could be completed within 1 to 10 working days. That is a direct application of the 8/80 rule. The 1/10 rule is related but expressed differently: work packages should usually represent between 1% and 10% of the project duration or effort, depending on the planning method. The reporting period rule links work package size to the frequency of performance reporting. The scenario specifically refers to the 8-hour and 80-hour thresholds, so the correct rule is unmistakably the 8/80 rule.

Reference topics: work breakdown structure, work package sizing, 8/80 rule, activity planning, scope decomposition.


Contribute your Thoughts:

0/2000 characters
I'm a bit lost on this one. I thought the reporting period rule was something different, but I can't remember the details.
upvoted 0 times
...
Paris
5 days ago
The 8/80 rule sounds familiar, and I feel like we practiced a similar question. It might be the correct option since it mentions the hours.
upvoted 0 times
...
Gerry
10 days ago
I think the 1/10 rule is about breaking down tasks into manageable sizes, but I can't recall the specifics. Maybe it's the answer?
upvoted 0 times
...
Iluminada
15 days ago
I remember discussing the 8/80 rule in class, but I'm not entirely sure if it applies here. It seems like it could be the right choice.
upvoted 0 times
...

Save Cancel