You are preparing to install a new 2-node AFF A250 system at a customer site with an existing cluster that uses NetApp CN1610 cluster interconnect switches.
In this scenario, what are two valid actions for this installation? (Choose two.)
A and B are valid options. The new nodes can be added to the existing cluster and switches, or a new 2-node switched cluster can be created using the CN1610 switches. I think option C is not valid since the question specifies an existing cluster using CN1610 switches.