A proposed six-story commercial building will have a basement level with finished floor 20'-0" below grade. The building site is located less than 1 mile from the coastline. A site survey indicates that the average site elevation is 5'-0" above sea level.

Based on the site-specific conditions, which four issues should the architect address in the design? Check the four that apply.

Suggested Answer: A, B, D, E

Comprehensive and Detailed

Dewatering during construction (A): The deep excavation (20' below grade) near sea level likely intersects the water table, necessitating dewatering to keep the site dry during construction.

Water table height (B): Proximity to the coast raises the water table, which affects foundation and waterproofing design.

Potential corrosion due to salt (D): Salt in water vapor and marine air can corrode metal exterior finishes and reinforcements; materials and coatings must be selected accordingly.

Hydrostatic pressure on basement walls (E): High water tables create significant lateral water pressure requiring robust waterproofing and structural resistance.

Spread footings (C) may or may not be suitable depending on soil but are not specific to coastal or basement conditions.

Radiant flooring (F) is unrelated to site conditions and more a mechanical choice.


ARE 5.0 PPD -- Environmental Conditions and Context, Site and Foundation Design

The Architect's Handbook of Professional Practice, 15th Edition -- Coastal and Marine Environment Design

Get Premium Project-Planning-Design Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
17 comments · newest first
LA
Lashaun 5 days ago
I think radiant flooring could help with moisture control, though.
BL
Blair 10 days ago
True, but radiant flooring seems unnecessary for this project.
RO
Roslyn 15 days ago
Spread footings might be less critical, but still worth mentioning.
LA
Lashaun 20 days ago
Yes! Salt can really damage finishes over time.
BL
Blair 26 days ago
Right! And potential corrosion from salt is a must-address issue too.
RO
Roslyn 1 month ago
I agree, but we can't ignore hydrostatic pressure on basement walls. It could be a disaster.
LA
Lashaun 1 month ago
Definitely! Water table height is also a big concern here.
BL
Blair 1 month ago
I think we need to consider dewatering during construction. It's crucial.
GE
Georgiana 2 months ago
Agreed, A and E are musts for sure!
AR
Aretha 2 months ago
C is important too, but I’m not sure about F.
CA
Carissa 2 months ago
Wait, how can the basement be 20' below grade if the site is only 5' above sea level?
VE
Verda 2 months ago
I think D is also a big concern with the saltwater nearby.
AA
Aaron 2 months ago
Definitely A, B, and E are crucial!
NO
Norah 2 months ago
I wonder if we should also think about potential corrosion from saltwater vapor. That could really impact the building materials over time.
TY
Ty 3 months ago
I feel like I’ve seen a question similar to this before, and I think hydrostatic pressure on basement walls is definitely something we need to consider.
LA
Lashaunda 3 months ago
I’m not entirely sure, but I think the water table height is also a big concern since the site is close to the coast. It could affect the basement.
DO
Donte 3 months ago
I remember discussing the importance of dewatering during construction, especially with a basement so deep. That seems like a critical issue to address.