A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE; Each correct selection is worth one point.
Scot
16 days agoChantell
20 days agoNoel
3 days agoArlen
26 days agoCoral
1 months agoSantos
10 days agoYuki
24 days agoJamie
30 days agoMarylin
2 months agoAlysa
12 days agoCammy
28 days agoLaurena
2 months agoKeneth
2 months agoLaurena
2 months ago