Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

Microsoft Exam 70-348 Topic 14 Question 4 Discussion

Actual exam question for Microsoft's 70-348 exam
Question #: 4
Topic #: 14
[All 70-348 Questions]

You are a project manager for an organization that uses Microsoft PPM. You plan each project in phases.

Team members must only see the assignments from a selected phase. All reports and project schedule views must reflect the entire project schedule, so the entire project is visible to the management team.

You need to configure Microsoft PPM.

What should you do?

Show Suggested Answer Hide Answer
Suggested Answer: D

Comments

Currently there are no comments in this discussion, be the first to comment!


Save Cancel