Which of the following is a typical work product that the Test Analyst would deliver as part of the test closure activities?[K2] 1 credit
A) A list of all deferred defects
B) A list of all rejected defect reports
C) A list of all defects found in production and fixed in this release
D) A list of all resolved defects

ISTQB ATA Exam - Topic 4 Question 110 Discussion

Actual exam question for ISTQB's ATA exam
Question #: 110
Topic #: 4
[All ATA Questions]

Which of the following is a typical work product that the Test Analyst would deliver as part of the test closure activities?

[K2] 1 credit

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

0/2000 characters
Tonette
4 days ago
I feel like the list of all defects found in production could be relevant, but it seems more like a post-release report rather than a closure activity.
upvoted 0 times
...
Gearldine
9 days ago
I remember practicing a question like this, and I think deferred defects were mentioned as part of closure, but I can't recall if they were the main focus.
upvoted 0 times
...
Janey
14 days ago
I think the test closure activities should include a list of all resolved defects, but I'm not entirely sure if that's the best option here.
upvoted 0 times
...

Save Cancel