Shripriya is defining the guidelines for the review process implementation in her company. Which of the following statements is LEAST likely to have been recommended by her?
C) Large sized work products should be reviewed in one go because you will have to spend too much time if you split it into multiple reviews.
A) Independent of the size of the work products, planning for the review should be performed
B) Review initiation is the stage when the review team starts the discussion on the review comments
D) Defect reports should be created for every review found

iSQI CTFL_Syll_4.0 Exam - Topic 3 Question 46 Discussion

Actual exam question for iSQI's CTFL_Syll_4.0 exam
Question #: 46
Topic #: 3
[All CTFL_Syll_4.0 Questions]

Shripriya is defining the guidelines for the review process implementation in her company. Which of the following statements is LEAST likely to have been recommended by her?

Show Suggested Answer Hide Answer
Suggested Answer: C

In a structured review process, it is essential to plan reviews carefully and manage them effectively. Reviewing large work products in one go is not recommended because it can lead to oversight of issues due to fatigue or information overload. It is more efficient to break down large work products into smaller, manageable parts and review them incrementally. This ensures a thorough and effective review process. Additionally, other practices such as planning for the review, starting discussions during review initiation, and creating defect reports for found issues are standard recommendations for an effective review process.

Top of Form

Bottom of Form


Contribute your Thoughts:

0/2000 characters
Matthew
1 month ago
D seems necessary. Defect reports are crucial for tracking.
upvoted 0 times
...
Kina
1 month ago
I feel A is also a bit off. Size shouldn't dictate planning.
upvoted 0 times
...
Ernestine
1 month ago
Agreed! C doesn't make sense. It leads to more issues.
upvoted 0 times
...
Gerald
2 months ago
I think C is the least likely. Splitting reviews is more efficient.
upvoted 0 times
...
Marva
2 months ago
B is pretty standard. Nothing surprising there.
upvoted 0 times
...
Tyra
2 months ago
Wait, C? Really? That sounds risky.
upvoted 0 times
...
Corinne
2 months ago
D is a must. Can't skip defect reports!
upvoted 0 times
...
Juliana
2 months ago
Definitely agree with A. Planning is key!
upvoted 0 times
...
Valentine
2 months ago
C seems off. Splitting reviews is usually better.
upvoted 0 times
...
Catarina
3 months ago
C) Large sized work products should be reviewed in one go because you will have to spend too much time if you split it into multiple reviews. Haha, good luck with that! Splitting it up is definitely the way to go.
upvoted 0 times
...
Nickie
3 months ago
B) Review initiation is the stage when the review team starts the discussion on the review comments. This seems like a reasonable recommendation for the review process.
upvoted 0 times
...
Catina
4 months ago
A) Independent of the size of the work products, planning for the review should be performed. This is a sensible recommendation that should be followed regardless of the work product size.
upvoted 0 times
...
Phyliss
4 months ago
D) Defect reports should be created for every review found. This is the most likely recommendation to ensure proper documentation and tracking of issues.
upvoted 0 times
...
Ronald
4 months ago
C) Large sized work products should be reviewed in one go because you will have to spend too much time if you split it into multiple reviews. This is clearly the least likely recommendation. Splitting large work products into multiple reviews is a better approach.
upvoted 0 times
...
Josphine
4 months ago
D makes sense because documenting defects is crucial, but I wonder if every single review needs a report.
upvoted 0 times
...
Shantell
4 months ago
C sounds off to me. I think splitting large reviews is usually better to manage feedback effectively.
upvoted 0 times
...
Lazaro
4 months ago
I’m not sure about B; it feels like the initiation stage should be more about setting up rather than discussing comments.
upvoted 0 times
...
Jerry
5 months ago
I remember something about planning reviews regardless of work product size, so A seems likely to be recommended.
upvoted 0 times
...
Frankie
5 months ago
Alright, I'm going to go with C as well. It just doesn't seem like a practical recommendation compared to the other options. Gotta be careful with those tricky "least likely" questions!
upvoted 0 times
...
Shawnna
5 months ago
I'm feeling pretty confident about this one. I think the answer is C - large work products should definitely be reviewed in multiple sessions, not all at once. That would be way too much to cover in one go.
upvoted 0 times
...
Lorenza
5 months ago
Yeah, I agree with you on that one. C seems like the outlier here. The other options sound more reasonable in terms of review process guidelines.
upvoted 0 times
...
Magda
5 months ago
Hmm, okay, let me think this through. I'm pretty sure C is the least likely one - reviewing large work products in one go doesn't sound like a good idea, it would be better to split it up.
upvoted 0 times
...
Pedro
5 months ago
I'm a bit confused about the phrasing of this question. It seems like they're asking us to identify the statement that is least likely to have been recommended, which is a bit tricky.
upvoted 0 times
William
27 days ago
I think C is the least likely recommendation.