Which ONE of the following options is aPRODUCT riskand NOT aPROJECT risk?
Product risksare risks thatimpact the quality or functionality of the software, whereasproject risksaffect theprocess, resources, or timeline.
(A) is correctbecause incorrect calculations impact software correctness.
(B), (C), and (D) are project risksas they relate toteam coordination, staffing, and schedulingrather than software defects.
Identifyingproduct risksearlyimproves defect detection and ensures better coverage for high-risk areas.