Your Agile team is developing a web-based system that will allow users to browse and buy online from a store's shopping catalogue. Continuous Integration has been implemented and technically it is working well, running several times per day, but each run is taking almost as much time as the team is prepared to allow. It is clear that after a few more iterations, as the number of tests needed grows with the product, it will be taking too much time.Which of the four options contains a pair of solutions that will BOTH help to solve this problem?a. Only include unit and component integration tests in the automated Cl runs.b. Schedule low priority tests to be the first ones executed in each run, in order to provide rapid build verification.c. Reduce the extent to which the automated tests go through the user interface, using technical interfaces instead.d. Reduce the number of Cl cycles run each day.e. Select a subset of automated tests for the daytime Cl runs, and run as many of the other tests as possible in an overnight cycle.SELECT ONE OPTION
C) c and e
A) d and e
B) b and d
D) a and c

iSQI CTAL-ATT Exam - Topic 8 Question 79 Discussion

Actual exam question for iSQI's CTAL-ATT exam
Question #: 79
Topic #: 8
[All CTAL-ATT Questions]

Your Agile team is developing a web-based system that will allow users to browse and buy online from a store's shopping catalogue. Continuous Integration has been implemented and technically it is working well, running several times per day, but each run is taking almost as much time as the team is prepared to allow. It is clear that after a few more iterations, as the number of tests needed grows with the product, it will be taking too much time.

Which of the four options contains a pair of solutions that will BOTH help to solve this problem?

a. Only include unit and component integration tests in the automated Cl runs.

b. Schedule low priority tests to be the first ones executed in each run, in order to provide rapid build verification.

c. Reduce the extent to which the automated tests go through the user interface, using technical interfaces instead.

d. Reduce the number of Cl cycles run each day.

e. Select a subset of automated tests for the daytime Cl runs, and run as many of the other tests as possible in an overnight cycle.

SELECT ONE OPTION

Show Suggested Answer Hide Answer
Suggested Answer: C

The ISTQB Advanced Level Agile Technical Tester syllabus emphasizes the importance of optimizing Continuous Integration (CI) processes in Agile environments. Option C suggests reducing the extent to which automated tests interact with the user interface and instead using technical interfaces, which is often faster as it bypasses the GUI layer. Additionally, running a subset of tests during the day and the rest overnight can help manage the CI process without overloading the system during peak hours. These strategies align with the best practices for maintaining efficient CI cycles and ensuring that the CI process remains sustainable as the number of tests grows with the product.

Reference= The ISTQB Advanced Level Agile Technical Tester documents and training resources provide guidelines on test automation approaches and continuous deployment and delivery, which are relevant to optimizing CI processes12.Moreover, best practices for continuous testing in Agile suggest prioritizing tests that provide fast feedback and running extensive test suites outside of peak hours3.