ISM LEAD Exam - Topic 2 Question 45 Discussion

Posted by Kami on Oct 13, 2026 at 07:07 PM

A chemical company sets a standard cost for a key component at $5 per unit. The firm values inventory at standard cost. The firm plans to purchase 10,000 units during the month of March, but at the end of the month, they realize they actually purchased 12,000 units, at a cost of $4.50 per unit.

What is the firm's Purchase Price Variance (PPV) for the month of March?

Suggested Answer: A

To calculate the Purchase Price Variance (PPV), use the following formula:

PPV=(ActualPriceStandardPrice)ActualQuantitytext{PPV} = (text{Actual Price} - text{Standard Price}) times text{Actual Quantity}PPV=(ActualPriceStandardPrice)ActualQuantity

Given:

Standard Price = $5.00 per unit

Actual Price = $4.50 per unit

Actual Quantity = 12,000 units

text{PPV} = ($4.50 - $5.00) times 12,000 text{PPV} = (-$0.50) times 12,000 text{PPV} = -$6,000.00

The negative sign indicates a favorable variance (cost savings). Hence, the PPV for the month of March is ($6,000.00). Leadership and transformation management documents emphasize the importance of variance analysis in controlling procurement costs and ensuring budget compliance. Reference highlight that monitoring PPV helps identify cost-saving opportunities and improve financial performance.


Get Premium LEAD Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
0 comments · newest first

Currently there are no comments in this discussion, be the first to comment!

0/2000 characters

Save Cancel