Which of the following refers to a procedure whereby data are collected and compared to requirements in order to make an acceptance decision?
B) Inspection
A) Process mapping
C) Internal audit
D) Peer review

ISM INTE Exam - Topic 3 Question 38 Discussion

Actual exam question for ISM's INTE exam
Question #: 38
Topic #: 3
[All INTE Questions]

Which of the following refers to a procedure whereby data are collected and compared to requirements in order to make an acceptance decision?

Show Suggested Answer Hide Answer
Suggested Answer: B

Inspection is the procedure where data is collected and compared to requirements to make an acceptance decision. This process ensures that products meet specified quality standards before acceptance, playing a critical role in quality control and compliance.


Contribute your Thoughts:

0/2000 characters
Iola
5 days ago
I was torn between B and C. But B feels more direct.
upvoted 0 times
...
Jennie
10 days ago
I agree, B) Inspection makes sense. It's about checking quality.
upvoted 0 times
...
Cecil
15 days ago
I think it's B) Inspection. Seems straightforward.
upvoted 0 times
...
Cecily
20 days ago
Definitely B) Inspection. It’s the most direct method for acceptance.
upvoted 0 times
...
Marg
26 days ago
I feel like A) Process mapping is too broad for this question.
upvoted 0 times
...
Reed
1 month ago
But isn’t D) Peer review about feedback? Not really acceptance.
upvoted 0 times
...
Dana
1 month ago
I’m leaning towards C) Internal audit. It’s more about compliance.
upvoted 0 times
...
Quentin
1 month ago
I agree, B) Inspection makes sense. It's about checking quality.
upvoted 0 times
...
Raymon
2 months ago
I think it's B) Inspection. Seems straightforward.
upvoted 0 times
...
Kerrie
2 months ago
Process mapping doesn't fit this description at all.
upvoted 0 times
...
Katina
2 months ago
Not sure about that, seems too simple for acceptance decisions.
upvoted 0 times
...
Erinn
2 months ago
Wait, I thought internal audits were for that?
upvoted 0 times
...
Veronika
2 months ago
Totally agree, it's all about checking against standards!
upvoted 0 times
...
Berry
2 months ago
B) Inspection is the right answer.
upvoted 0 times
...
Hassie
3 months ago
Not sure about this one. Could it be A) Process mapping instead?
upvoted 0 times
...
Maurine
3 months ago
Totally agree with B) Inspection! It’s all about checking standards.
upvoted 0 times
...
Tesha
3 months ago
Wait, is it really just about comparing to requirements? Sounds too simple!
upvoted 0 times
...
Latanya
5 months ago
I thought it was C) Internal audit. Seems like a fit too.
upvoted 0 times
...
Jacqueline
5 months ago
Definitely B) Inspection. That's the right term!
upvoted 0 times
...
Kent
5 months ago
Peer review seems more about feedback rather than making acceptance decisions, so I'm leaning towards B) Inspection as well.
upvoted 0 times
...
Raina
5 months ago
I feel like process mapping is more about visualizing workflows, so it probably isn't the right choice here.
upvoted 0 times
...
Peggy
5 months ago
I remember something about internal audits being related to compliance, but I can't recall if they fit this definition.
upvoted 0 times
...
Lore
6 months ago
I think the answer might be B) Inspection, but I'm not entirely sure. It sounds familiar from our last practice quiz.
upvoted 0 times
...

Save Cancel