ISM Exam CPSM1 Topic 2 Question 91 Discussion

Actual exam question for ISM's CPSM1 exam
Question #: 91
Topic #: 2
[All CPSM1 Questions]

A project manager is assigned to a project, either full-time or part-time, depending onthe size of the project, and then must negotiate for the services of individual teammembers with each appropriate functional manager in:

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Solange
4 days ago
I'm not sure, but I think C) Project Organization could also be a possibility. Project managers are assigned to projects in project organizations.
upvoted 0 times
...
Marti
5 days ago
I agree with Suzi. In a matrix organization, project managers negotiate for team members with functional managers.
upvoted 0 times
...
Vinnie
7 days ago
B) Matrix Organization, definitely! That's where the project manager has to navigate the complex web of functional and project responsibilities. I can already feel the headache coming on just thinking about it.
upvoted 0 times
...
Suzi
16 days ago
I think the answer is B) Matrix Organization.
upvoted 0 times
...