Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

ISC2 CAP Exam - Topic 9 Question 36 Discussion

Posted by Glenn on May 09, 2022 at 08:58 PM

You are the project manager of the NNN project for your company. You and the project team are working together to plan the risk responses for the project. You feel that the team has successfully completed the risk response planning and now you must initiate what risk process it is. Which of the following risk processes is repeated after the plan risk responses to determine if the overall project risk has been satisfactorily decreased?

Suggested Answer: D

Get Premium CAP Questions as Interactive Web-Based Practice Test or PDF Real Exam Format Detailed Explanations Instant Access Get Your Practice Test
12 comments · newest first
CO
Cory 11 months ago
B is also a valid point, but I lean towards D for this one.
DE
Desmond 12 months ago
Wait, are we sure it's not A? Seems like we should identify risks again.
SH
Shannon 12 months ago
Totally agree with D! Makes sense to measure the impact.
RI
Ria 12 months ago
I thought it was C, Risk response implementation.
OZ
Ozell 1 year ago
It's definitely D, Quantitative risk analysis!
JU
Julio 1 year ago
I'm a bit lost on this one. I thought we always go back to risk identification, but that doesn't seem right after planning responses.
FL
Florinda 1 year ago
I practiced a question similar to this, and I think it was about assessing the effectiveness of the responses, which might point to risk response implementation.
MA
Margart 1 year ago
I think after planning the risk responses, we need to check if the risks have been effectively managed, so maybe it's the risk response implementation?
VO
Von 1 year ago
I remember something about qualitative and quantitative analysis, but I'm not sure which one comes after planning. It feels like both could fit here.
YO
Youlanda 1 year ago
Hmm, I'm a little unsure about this one. I need to think through the definition of a basic service set and how that relates to the components of a network.
DA
Dahlia 1 year ago
I'm pretty confident that C is the right answer here. Blast Extreme and PCoIP are the go-to protocols for GPU-accelerated remote desktops, which is what this question is asking about. The other options include some less relevant protocols.
LI
Linwood 1 year ago
I agree with Sarah. The number of tests needing maintenance is the most direct way to assess the effort required. The other metrics are interesting, but don't seem as closely tied to the goal.
0/2000 characters