ISC2 CAP Exam - Topic 6 Question 60 Discussion
You work as a project manager for BlueWell Inc. You with your team are using a method or a (technical) process that conceives the risks even if all theoretically possible safety measures would be applied. One of your team member wants to know that what is a residual risk. What will you reply to your team member?
B) It is a risk that remains after planned risk responses are taken.
A) It is a risk that remains because no risk response is taken.
C) It is a risk that cannot be addressed by a risk response.
D) It is a risk that will remain no matter what type of risk response is offered.