Isaca Exam CISA Topic 7 Question 73 Discussion

Actual exam question for Isaca's Certified Information Systems Auditor exam
Question #: 73
Topic #: 7
[All Certified Information Systems Auditor Questions]

During a project audit, an IS auditor notes that project reporting does not accurately reflect current progress. Which of the following is the GREATEST resulting impact?

Show Suggested Answer Hide Answer
Suggested Answer: C

Comments

Carey
17 hours ago
I disagree, I think B is the biggest impact. If the board of directors isn't getting the full picture, they could make some really bad decisions that could derail the entire project.
upvoted 0 times
...
Gwen
2 days ago
Oh man, this question is a tricky one. Inaccurate project reporting? That's a major issue. I'm leaning towards C, because if the steering committee can't provide effective governance, the whole project could go off the rails.
upvoted 0 times
...

Save Cancel