The following is a list of major findings in the executive summary report for an audit of the contract management process
- Noncompliance with contract provisions requiring vendors to obtain insurance policies with indemnity value of not less than $1 million
- Compliance with contract obligations and deliverables is not monitored
- No contract agreement with five vendors providing core services
Which of the following is an appropriate conclusion that can be drawn from these findings?