IFPUG Exam I40-420 Topic 1 Question 107 Discussion

Actual exam question for IFPUG's I40-420 exam
Question #: 107
Topic #: 1
[All I40-420 Questions]

An application originally valued at 327 FP was enhanced. The enhancement added 3 low EQs, 2 low EIs, 2 high EOs, and changed 3 low ILFs. What is the enhancement project functional size?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Herminia
4 days ago
This question is giving me a headache. Are we supposed to be FP counting wizards or something? I'm just going to guess C and hope for the best.
upvoted 0 times
...
Dierdre
12 days ago
I'm going with D. The original application was 327 FP, and the changes seem to add up to 50 FP, so the total enhancement project functional size should be 377 FP.
upvoted 0 times
...
Jina
16 days ago
I'm not sure, but I think the answer might be B) 50.
upvoted 0 times
...
Carma
17 days ago
Hmm, I think the answer is B. The enhancement added 3 low EQs, 2 low EIs, and 2 high EOs, which seems to add up to 50 FP based on the IFPUG counting rules.
upvoted 0 times
...
Anika
19 days ago
I disagree, I believe the answer is D) 377.
upvoted 0 times
...
Selene
20 days ago
I think the answer is C) 356.
upvoted 0 times
...