New Year Sale 2026! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

IBM C1000-132 Exam - Topic 4 Question 30 Discussion

Actual exam question for IBM's C1000-132 exam
Question #: 30
Topic #: 4
[All C1000-132 Questions]

In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?

Show Suggested Answer Hide Answer
Suggested Answer: C

In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.


Contribute your Thoughts:

0/2000 characters
Vashti
3 months ago
I thought it was based on the Job Plan start date plus duration.
upvoted 0 times
...
Edison
3 months ago
I agree with Theron, A is the way to go!
upvoted 0 times
...
Francene
3 months ago
Wait, is it really calculated that way? Sounds off.
upvoted 0 times
...
Janella
4 months ago
I think it's the PM target finish date, right?
upvoted 0 times
...
Theron
4 months ago
It's definitely the Job Plan finish date!
upvoted 0 times
...
Georgeanna
4 months ago
I feel like the answer could be the Job Plan start date plus the duration, but I need to double-check my notes on that.
upvoted 0 times
...
Roselle
4 months ago
I’m a bit confused about whether it’s the PM target finish date or the Job Plan start date that plays a bigger role in this calculation.
upvoted 0 times
...
Sherrell
4 months ago
I remember practicing a question similar to this, and I think the finish date is calculated from the Work Order target start date plus the Job Plan duration.
upvoted 0 times
...
Haydee
5 months ago
I think the target finish date might be related to the Job Plan finish date, but I'm not entirely sure if that's the right option.
upvoted 0 times
...
Kanisha
5 months ago
I've got a good feeling about this one. Based on the options, it seems like the target finish date is calculated by taking the Work Order target start date and adding the Job Plan duration. I'll go with option C.
upvoted 0 times
...
Lindy
5 months ago
I think the key here is understanding the relationship between the Work Order and the Preventive Maintenance record. The question states that the Work Order is generated from a PM record, so the target finish date is likely based on information from the PM record.
upvoted 0 times
...
Mi
5 months ago
I'm a bit confused by the wording of the question. Is it asking about the target finish date of the Work Order or the Preventive Maintenance record? I'll need to re-read the options to make sure I understand the context.
upvoted 0 times
...
Mollie
5 months ago
Okay, let me see if I can break this down. The question is asking about how the target finish date is calculated, so I need to focus on the different date fields mentioned in the options.
upvoted 0 times
...
Carin
5 months ago
Hmm, this seems like a straightforward question about how the target finish date is calculated for a Work Order. I'll need to think through the different options carefully.
upvoted 0 times
...
Sharan
5 months ago
Hmm, I'm a bit unsure about this one. I'll need to think it through step-by-step to make sure I understand the context and what the question is asking.
upvoted 0 times
...
Mira
5 months ago
This reminds me of a practice question where IAM was mentioned in the context of account security. I feel pretty confident it's the answer.
upvoted 0 times
...
Colette
2 years ago
My money's on C. Combining the Work Order start date and the Job Plan duration just makes sense. Anything else would be too easy.
upvoted 0 times
...
Torie
2 years ago
Ha! As if the developers would make it that simple. C is probably the correct answer, but who knows what hidden formula they've cooked up.
upvoted 0 times
...
Ashlyn
2 years ago
Hmm, I'm not sure about this one. Maybe D is the right answer since the Job Plan start and duration are involved.
upvoted 0 times
Ernest
1 year ago
I agree with you, D seems like the correct answer based on the information provided.
upvoted 0 times
...
Cassie
1 year ago
I'm not sure either, but I think D makes sense since it involves the Job Plan start date and duration.
upvoted 0 times
...
Cherry
2 years ago
I believe it's A because the Job Plan finish date is used to calculate the target finish date.
upvoted 0 times
...
Jerilyn
2 years ago
I think it's C because it involves the Work Order target start date and the Job Plan duration.
upvoted 0 times
...
...
Johnathon
2 years ago
Option B seems logical to me. The target finish date should be derived from the PM target finish date.
upvoted 0 times
Makeda
2 years ago
I believe it's the Job Plan finish date that determines the target finish date.
upvoted 0 times
...
Adaline
2 years ago
I think it should be a combination of the PM target finish date and the Work Order target start date.
upvoted 0 times
...
Leonor
2 years ago
I agree, option B makes sense. The target finish date should be based on the PM target finish date.
upvoted 0 times
...
...
Merlyn
2 years ago
I'm not sure, but I think it might be the Job Plan finish date.
upvoted 0 times
...
Doyle
2 years ago
I believe it's actually calculated using the Work Order target start date + the Job Plan duration.
upvoted 0 times
...
Eladia
2 years ago
I think the answer is C. The target finish date should be calculated based on the Work Order target start date and the Job Plan duration.
upvoted 0 times
Mona
2 years ago
Yes, that's correct. It's the Work Order target start date + the Job Plan duration.
upvoted 0 times
...
Felicitas
2 years ago
I agree, the target finish date is calculated based on the Work Order target start date and the Job Plan duration.
upvoted 0 times
...
...
Reena
2 years ago
I think the target finish date is calculated based on the PM target finish date.
upvoted 0 times
...

Save Cancel