The ECC800-Pro is the core component for FusionModule2000 local management. Southbound components can be using the PoE bus.
If multiple SmartLi battery cabinets are combined, press and hold the POWER ON/OFF button on each battery management module for more than 2s, and then switch on the battery circuit breaker in any cabinet to start all battery cabinets.
To modify the FusionModule2000 plan view of the ECC800-Pro, users need to log in to the WebUI as admin account.
A data center is at the Tier IV level and uses Huawei FusionModule2000 smart module. In this smart module, the PDU8000 integrated PDF cannot be used to supply power to IT loads and precision air conditioners at the same time because isolation requirements are not met.