Before the gNode configuration is adjusted, in order to avoid alarm reporting and display in the network management foreground, the project status cannot be set to which of the following states?
B) Normal state
A) Expansion status
C) Commissioning status
D) Extension status

Huawei H35-460 Exam - Topic 3 Question 75 Discussion

Actual exam question for Huawei's H35-460 exam
Question #: 75
Topic #: 3
[All H35-460 Questions]

Before the gNode configuration is adjusted, in order to avoid alarm reporting and display in the network management foreground, the project status cannot be set to which of the following states?

Show Suggested Answer Hide Answer
Suggested Answer: B