Which of the following can be used to start the inverter of the UPS5000-H?
A) UPS WebUI and C) UPS LCD
B) ECC
D) NetEco

Huawei H20-923_V1.0 Exam - Topic 9 Question 10 Discussion

Actual exam question for Huawei's H20-923_V1.0 exam
Question #: 10
Topic #: 9
[All H20-923_V1.0 Questions]

Which of the following can be used to start the inverter of the UPS5000-H?

Show Suggested Answer Hide Answer
Suggested Answer: A, C

For the Huawei UPS5000-H, inverter startup is executed through the UPS's own control interfaces, which provide the ''Running Control / Inv. ON'' operation with the required confirmations and permissions. The UPS LCD (MDU touchscreen) supports inverter startup through menu operations such as selecting inverter start functions and confirming the action after authentication. The UPS WebUI also provides the same operational control path, where an operator logs in and issues the Inv. ON command under the UPS monitoring/running control pages. These two interfaces are part of the UPS monitoring and control design and are explicitly used for commissioning and routine O&M actions.

By contrast, ECC (data center controller) and NetEco (management platform) are mainly used for site-level monitoring, alarm collection, visualization, reporting, and centralized management. While they can display UPS status and alarms (and may integrate with UPS data), inverter startup is defined as a UPS running control operation performed on the UPS's LCD or WebUI control plane to ensure proper authorization, safety checks, and command traceability.


Contribute your Thoughts:

0/2000 characters
A) UPS WebUI is correct!
upvoted 0 times
...
Ashlyn
5 days ago
I don't think NetEco is used for starting the inverter; it seems more focused on monitoring and management.
upvoted 0 times
...
Tanja
10 days ago
I feel like the UPS LCD could be an option too, but I can't recall if it actually has that capability.
upvoted 0 times
...
Kathryn
15 days ago
I'm not entirely sure, but I remember something about the ECC being involved in starting systems.
upvoted 0 times
...
Delsie
2 months ago
I think the UPS WebUI might be the right choice since we used it in a similar practice question about remote management.
upvoted 0 times
...

Save Cancel