Which of the following operations need to be performed before deployment in Easy mode? (Select All that Apply)
The Easy mode in Huawei's iMaster NCE-Fabric simplifies VXLAN fabric deployment with automated configuration. Certain pre-deployment steps are required. Let's evaluate each option:
A . Disable data synchronization upon going online for the first time: This is false. Data synchronization is typically enabled by default to ensure consistency; disabling it is not a standard pre-deployment step and is optional based on specific needs. FALSE.
B . Load the license: This is true. A valid license must be loaded into iMaster NCE-Fabric before deployment to unlock features, including Easy mode functionality. TRUE.
C . Pre-configure the access ports: This is true. Access ports on devices (e.g., server leaf nodes) need to be pre-configured (e.g., with VLANs or basic settings) to ensure connectivity before Easy mode automation begins. TRUE.
D . Configure an SSH fingerprint verification policy: This is false. SSH fingerprint verification is part of security configuration but is not a mandatory pre-deployment step for Easy mode; it can be set post-deployment or is automated. FALSE.
Thus, B (Load the license) and C (Pre-configure the access ports) are required operations before deployment in Easy mode.
Lorenza
10 months agoStefania
10 months agoBlair
10 months agoNida
11 months agoBrendan
11 months agoHildegarde
11 months agoEdelmira
11 months agoLasandra
11 months agoBok
12 months agoTrevor
12 months agoAleisha
12 months agoFabiola
12 months agoKasandra
12 months agoIsaac
12 months ago