Independence Day Deal! Unlock 25% OFF Today – Limited-Time Offer - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC Exam GISF Topic 3 Question 51 Discussion

Actual exam question for GIAC's GISF exam
Question #: 51
Topic #: 3
[All GISF Questions]

The executive team wants you to track labor costs for your project as well as progress on task

completion and the resulting dates. What information must you update for tasks to provide this

information?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Norah
1 months ago
Come on, people, this is a no-brainer. Obviously, the answer is C. Anything less, and you're just setting yourself up for a headache. Tracking all the details is the way to go!
upvoted 0 times
...
Eun
1 months ago
Hmm, I'm torn between C and D. Actual Start, Actual Work, and Remaining Work sounds like a lot of data to manage. Maybe D is the way to go - less is more!
upvoted 0 times
Lindsey
1 days ago
I agree with you, C seems like the most comprehensive option for tracking labor costs and progress on tasks.
upvoted 0 times
...
Luisa
4 days ago
I think C is the way to go. Actual Start, Actual Work, and Remaining Work provide a more detailed picture of the project progress.
upvoted 0 times
...
...
Elvera
1 months ago
B is my pick. Actual Start and Percent Complete should give me what I need without all the extra fields. Keep it simple, right?
upvoted 0 times
Iluminada
26 days ago
I also think B is the best option. Actual Start and Percent Complete are key indicators for tracking labor costs and progress.
upvoted 0 times
...
Adell
27 days ago
I think C might be better. Actual Start, Actual Work, and Remaining Work provide a more detailed view of the project progress.
upvoted 0 times
...
Yuki
1 months ago
I agree, B is the way to go. It's simple and gives us the information we need.
upvoted 0 times
...
...
Arminda
2 months ago
I'm going with D. Actual Start, Percent Complete, and Remaining Duration. Percent Complete is a key metric for tracking progress, and Remaining Duration helps with forecasting.
upvoted 0 times
Jesusita
13 days ago
I'm not sure, but I think B could also be a valid option. Actual Start and Percent Complete can help in tracking progress effectively.
upvoted 0 times
...
Paz
1 months ago
I agree with you, C seems like a good choice. Actual Start and Actual Work give a clear picture of the labor costs involved.
upvoted 0 times
...
Milly
1 months ago
I think C is the right answer. Actual Start, Actual Work, and Remaining Work are important for tracking labor costs and progress.
upvoted 0 times
...
...
Paris
2 months ago
Option C seems like the most comprehensive answer. Actual Start, Actual Work, and Remaining Work would give me the information I need to track labor costs and task completion progress.
upvoted 0 times
Izetta
19 days ago
It's important to update Actual Start, Actual Work, and Remaining Work regularly to stay on top of project progress.
upvoted 0 times
...
Christene
1 months ago
Actual Start, Actual Work, and Remaining Work provide a clear picture of both labor costs and task completion.
upvoted 0 times
...
Nicolette
1 months ago
I think Actual Start, Actual Work, and Remaining Work are the key data points needed for accurate tracking.
upvoted 0 times
...
Paz
2 months ago
I agree, option C covers all the necessary information for tracking labor costs and task progress.
upvoted 0 times
...
...
Emilio
3 months ago
I think the answer is D) Actual Start, Percent Complete, and Remaining Duration because it provides a comprehensive view of labor costs and progress.
upvoted 0 times
...
Paul
3 months ago
I disagree, I believe the answer is A) Start, Work, and Remaining Work.
upvoted 0 times
...
Edgar
3 months ago
I think the answer is C) Actual Start, Actual Work, and Remaining Work.
upvoted 0 times
...

Save Cancel