Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

GIAC GCPM Exam - Topic 7 Question 83 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 83
Topic #: 7
[All GCPM Questions]

You are the project manager for company Inc. Your project has a budget at completion of $950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Jesse
4 days ago
I think the earned value here would be 50% of the budget, which is $475,000, right? So, if we divide that by the actual cost, we should get the CPI.
upvoted 0 times
...
Rodrigo
9 days ago
I remember we practiced calculating the cost performance index, but I’m not entirely sure about the formula. Is it just earned value divided by actual cost?
upvoted 0 times
...

Save Cancel