You are the project manager for company Inc. Your project has a budget at completion of $950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost performance index?
D) 0.95
A) 0.84
B) 0.86
C) 0.98

GIAC GCPM Exam - Topic 7 Question 83 Discussion

Actual exam question for GIAC's GCPM exam
Question #: 83
Topic #: 7
[All GCPM Questions]

You are the project manager for company Inc. Your project has a budget at completion of $950,000 and is 45 percent complete, though the project should be 50 percent complete. The project has spent $450,897 to reach the 45 percent complete milestone. What is the project's cost performance index?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

0/2000 characters
Bernardine
3 days ago
Right! EV is 50% of $950,000, which is $475,000.
upvoted 0 times
...
Kimi
8 days ago
Sure! It’s calculated as EV/AC.
upvoted 0 times
...
Julianna
13 days ago
Why A? Can you explain?
upvoted 0 times
...
Kimi
19 days ago
I’m leaning towards option A, 0.84.
upvoted 0 times
...
Bernardine
24 days ago
I think the CPI is crucial for understanding costs.
upvoted 0 times
...
Julianna
29 days ago
This question is tricky! I feel a bit lost.
upvoted 0 times
...
Janessa
1 month ago
Totally agree, that CPI calculation looks off!
upvoted 0 times
...
Stephania
1 month ago
Wait, how did they spend almost half a million and only get to 45%?
upvoted 0 times
...
Tawny
1 month ago
I think the CPI is around 0.84.
upvoted 0 times
...
Louis
2 months ago
45% complete but should be 50%? That's not great.
upvoted 0 times
...
Derick
2 months ago
The budget at completion is $950,000.
upvoted 0 times
...
Reynalda
2 months ago
I’m leaning towards option B, but I’m not confident. I think I need to double-check my calculations for the CPI before I finalize my answer.
upvoted 0 times
...
Annabelle
4 months ago
I feel like I’ve seen a similar question before, but I can’t recall if we should be concerned about the percentage completion when calculating CPI. Does it affect the earned value?
upvoted 0 times
...
Jesse
4 months ago
I think the earned value here would be 50% of the budget, which is $475,000, right? So, if we divide that by the actual cost, we should get the CPI.
upvoted 0 times
...
Rodrigo
4 months ago
I remember we practiced calculating the cost performance index, but I’m not entirely sure about the formula. Is it just earned value divided by actual cost?
upvoted 0 times
...